Progress in construction

1
stage
2%
2
stage
3%
3
stage
3%
4
stage
3%
5
stage
2%
6
stage
2%

Progress in construction RC "Lypynsky", October 2024

• concreting of vertical elements of columns and monolithic walls of the basement floor of sections 2 and 3;

• digging a pit for section 4;

• knitting of the reinforcing cage for the foundation slab of section 4;

• arrangement of horizontal formwork for the floor slab above the basement of sections 2 and 3;

• knitting reinforcement for the floor slab over the basement of 2 and 3 sections;

• digging a pit for the second tower crane and for section 6.