Progress in construction

1
stage
0%
2
stage
6%
3
stage
6%
4
stage
4%
5
stage
3%
6
stage
3%

Progress in construction RC "Lypynsky", February 2025

• concreting and reinforcement of the floor slab above the 2nd floor in 2-3 sections;

• concreting of vertical elements (columns and walls) of the 3rd floor in 2-3 sections;

• installation of formwork for the floor slab over the 3rd floor of 2-3 sections;

• concreting of the floor slab over the 3rd floor in 2-3 sections;

• concreting of vertical elements (columns and walls) on the 1st floor, 4 sections;

• installation of formwork under the floor slab over the 1st floor of the 4th section (40% complete);

• concreting of vertical elements (columns and walls) of the basement floor in 5-6 sections (40% complete);

• reinforcement knitting of the foundation slab in  the intermediate section;

• concreting and reinforcing the first part of the foundation slab for the parking lot.