• concreting and reinforcement of the floor slab above the 2nd floor in 2-3 sections;
• concreting of vertical elements (columns and walls) of the 3rd floor in 2-3 sections;
• installation of formwork for the floor slab over the 3rd floor of 2-3 sections;
• concreting of the floor slab over the 3rd floor in 2-3 sections;
• concreting of vertical elements (columns and walls) on the 1st floor, 4 sections;
• installation of formwork under the floor slab over the 1st floor of the 4th section (40% complete);
• concreting of vertical elements (columns and walls) of the basement floor in 5-6 sections (40% complete);
• reinforcement knitting of the foundation slab in the intermediate section;
• concreting and reinforcing the first part of the foundation slab for the parking lot.