Progress in construction

1
stage
0%
2
stage
6%
3
stage
6%
4
stage
4%
5
stage
3%
6
stage
3%

Progress in construction RC "Lypynsky", December 2024

• concreting of the floor slab above the first floor in 2-3 sections;

• concreting of vertical elements of the column walls of the second floor in 2-3 sections;

• concreting of vertical elements of columns and walls in the basement of the 4th section;

• installation of formwork for the floor slab above the basement in 4th section;

• excavation of the pit for sections 5-6 and intermediate section has been completed;

• concrete preparation in sections 5-6 and intermediate section has been arranged;

• installation of formwork and tying of reinforcement of the foundation slab for section 6;

• concreting of the foundation slab of sections 5-6 has been completed.