1
stage
2%
• vertical reinforcement and pouring of vertical elements of the basement floor, where the shelter will be arranged, has been completed;
• water lowering of 4-6 sections has been completed;
• waterproofing of the foundation slab and grounding of sections 2 and 3 have been completed;
• arrangement of the reinforced floor of the basement and the shelter has begun;
• development of the pit for sections 4 and 5 has begun.