Progress in construction

1
stage
0%
2
stage
6%
3
stage
6%
4
stage
4%
5
stage
3%
6
stage
3%

Progress in construction RC "Lypynsky", September 2024

• vertical reinforcement and pouring of vertical elements of the basement floor, where the shelter will be arranged, has been completed;

• water lowering of 4-6 sections has been completed;

• waterproofing of the foundation slab and grounding of sections 2 and 3 have  been completed;

• arrangement of the reinforced floor of the basement and the shelter has begun;

• development of the pit for sections 4 and 5 has begun.