• concreting of vertical elements of the 5th floor in 2-3 sections;
• concreting of the floor slab over the 5th floor in 2-3 sections;
• concreting of vertical elements of 2-3 floors in 4th section;
• concreting of the floor slab over the 2nd floor in 4th section;
• concreting of horizontal elements of the floor slab over the basement floor of the intermediate section;
• concreting of vertical elements of the 1st floor of the intermediate section (70% complete);
• concreting of the floor slab over the parking lot (second part);
• concreting of vertical elements of the basement floor in 5-6 sections;
• concreting of horizontal elements - beams for the floor slab above the basement floor of section 5;
• digging a pit for a new transformer substation.