Progress in construction

1
stage
0%
2
stage
9%
3
stage
9%
4
stage
8%
5
stage
5%
6
stage
5%

Progress in construction RC "Lypynsky", April 2025

•  concreting of vertical elements of the 5th floor in 2-3 sections;

•  concreting of the floor slab over the 5th floor in 2-3 sections;

•  concreting of vertical elements of 2-3 floors in 4th section;

•  concreting of the floor slab over the 2nd floor in 4th section;

•  concreting of horizontal elements of the floor slab over the basement floor of the intermediate section;

•  concreting of vertical elements of the 1st floor of the intermediate section (70% complete);

•  concreting of the floor slab over the parking lot (second part);

•  concreting of vertical elements of the basement floor in 5-6 sections;

•  concreting of horizontal elements - beams for the floor slab above the basement floor of section 5;

•  digging a pit for a new transformer substation.