Sections 2 and 3
• concreting of vertical elements (columns and walls) on the 6th floor;
• concreting of the floor slab above the 6th floor;
• concreting of staircases from 1 to 3 floors (section 2);
• concreting of stairwells from 1 to 7 floors (section 3);
• laying of the walls on the 2nd floor (95% complete);
• laying of the walls on the 3rd floor (40% complete);
• laying of ventilation units on the 2nd floor (40% complete).
Section 4
• concreting of the floor slab above the 3rd floor;
• concreting of vertical elements on the 4th floor;
• concreting of the floor slab over the 4th floor;
• concreting of vertical elements on the 5th floor (40% complete).
Intermediate section
• concreting of vertical elements on the 1st floor;
• concreting of the floor slab above the 1st floor;
• concreting of vertical elements on the 2nd floor (30% complete);
• concreting of the staircase from the basement to the 1st floor.
Sections 5 and 6
• concreting beams for the floor slab above the basement (section 5);
• concreting of vertical elements in the basement;
• installation of formwork and tying of reinforcement for the floor slab over the basement.
Transformation substation
• arrangement of the foundation from solid foundation blocks;
• vertical waterproofing of the basement walls (2-4 sections);
• backfilling of the pit sinuses around the walls of sections 2-4 (50% complete).