Progress in construction

1
stage
0%
2
stage
9%
3
stage
9%
4
stage
8%
5
stage
5%
6
stage
5%

Progress in construction RC "Lypynsky", June 2025

Sections 2 and 3

•  concreting of vertical elements (columns and walls) on the 6th floor;

•  concreting of the floor slab above the 6th floor;

•  concreting of staircases from 1 to 3 floors (section 2);

•  concreting of stairwells from 1 to 7 floors (section 3);

•  laying of the walls on the 2nd floor (95% complete);

•  laying of the walls on the 3rd floor (40% complete);

•  laying of ventilation units on the 2nd floor (40% complete).

Section 4

•  concreting of the floor slab above the 3rd floor;

•  concreting of vertical elements on the 4th floor;

•  concreting of the floor slab over the 4th floor;

•  concreting of vertical elements on the 5th floor (40% complete).

Intermediate section 

•  concreting of vertical elements on the 1st floor;

•  concreting of the floor slab above the 1st floor;

•  concreting of vertical elements on the 2nd floor (30% complete);

•  concreting of the staircase from the basement to the 1st floor.

Sections 5 and 6 

•  concreting beams for the floor slab above the basement (section 5);

•  concreting of vertical elements in the basement;

•  installation of formwork and tying of reinforcement for the floor slab over the basement.

Transformation substation

•  arrangement of the foundation from solid foundation blocks;

•  vertical waterproofing of the basement walls (2-4 sections);

•  backfilling of the pit sinuses around the walls of sections 2-4 (50% complete).