Progress in construction

1
stage
0%
2
stage
9%
3
stage
9%
4
stage
8%
5
stage
5%
6
stage
5%

Progress in construction RC "Lypynsky", March 2025

• concreting and reinforcement of the floor slab above the 2nd floor in 2-3 sections;

• concreting of vertical elements (columns and walls) of the 3rd floor in 2-3 sections;

• concreting of the floor slab over the 3rd and 4th floors in 2-3 sections;

• concreting of vertical elements of the 4th floor in 2-3 sections;

• concreting of the floor slab over the 1st floor in 4th section;

• concreting of vertical elements (columns and walls) of the 2nd floor, 4th section;

• concreting of the foundation slab for the intermediate two-story section;

• concreting of vertical elements of the basement floor of the intermediate section;

• installation of formwork for the floor slab above the basement of the intermediate section;

• concreting the second part of the foundation slab for the parking lot;

• concreting of vertical elements of the parking lot;

• installation of formwork for the floor slab above the parking lot;

• reinforcement of the floor slab over the first part of the parking lot (75% complete);

• concreting of vertical elements of the basement floor in 5-6 sections (70% complete);

• the first stage of waterproofing works on the vertical walls of the basement in 2-4 sections.