THE RC CRYSTAL AVENUE CONSTRUCTION: THE ROOF OF THE IV HOUSE IS COMPLETED

18.01.2023

The winter period did not become an obstacle to the continuation of the residential complex Crystal Avenue construction. So let's talk about the current state of affairs at the construction site of the complex.

In the second phase (11-A, Oksamytova St.) decoration of the hall, which is 60% ready, is in progress. Work on connecting power supply networks is also underway.

In the fourth phase (1, Kryshtaleva St.) the installation of the ventilated facade (70% complete) and the installation of the wet facade (65% complete) are ongoing. The arrangement of the roof is completely finished.

Another type of work, which does not concern individual buildings, but the entire complex, was the completion of the sewage networks relocation, which is necessary to meet the technical conditions for connection. The works were carried out in Oksamytova street. 