We are introducing you to the current state of affairs at the construction site of the residential complex "Crystal Avenue" in Petropavlivska Borshchahivka.
In the second phase (11-A, Oksamytova St.) finishing of the hall, works on connection of power supply networks and improvement of the territory and waterproofing works are ongoing.
In the fourth phase (1, Kryshtaleva St.) the installation of the ventilated facade (80% complete) and the installation of the wet facade (75% complete) are ongoing. The gasification of the house (50% ready) and the installation of fire equipment (80% ready) have started.
In the fifth phase (1-B, Kryshtaleva St.) monolithic works on the 18th floor and brickwork on the 9th floor are ongoing.