Here we tell you about the most notable achievements of the last six months on the construction site of the residential complex “Crystal Avenue”.

In the second phase (11-A, Oksamytova St.) facade and finishing works proceed. Installation of elevators has begun.

In the third phase (1-A,  Kryshtaleva St.) improvement of the adjacent territory (laying of paving slabs) proceeds.

In the fourth phase (1, Kryshtaleva St.)  window frames have been installed on the 12th floor. The brickwork is almost completed. Plastering works on 2-4 floors proceed.

In the fifth phase (1 – B, Kryshtaleva St.) the floor slab of the first floor has been completed.

The construction of the second part of the underground parking lot is also underway. Work on the entrance groups is currently underway there.