Monolithic works on the third building of the residential complex have been completed. In addition, work on the masonry of the exterior walls is gradually approaching the final. It lasts on the 11th and 14-17 floors. Masonry is being performed starting from the outer walls, as one of the next stages is the windows installation, and now active preparations are underway for this. In general, the masonry of the external walls (as well as the roof) will last only 20 days, which means a high pace of work on the project.
Other scope of work:
•Sewer elements are currently being installed. Vertical stacks are almost ready - by 75%.
•A fire water supply system for the house is being installed.
•Ventilation ducts and smoke extraction system will be ready within 10 days.
It should be mentioned separately that the preparation for the start of work on the underground parking lot is coming to an end. Work on this element of infrastructure will begin in a day or two.
Already in November, most of the work will be done to bring communications to the house. Soon water, gas and electricity will be here. Also, according to the plan, the first stage of roof installation will be completed by December 5. The work on the construction of the sidewalk and the road from Trakt-Hlynyanskyi Street to the first residential building will begin much earlier. This will even better combine the infrastructure of the complex with the road junction of the district, which is extremely convenient and important for the residents of the residential complex.