We continue to inform you about the construction progress of the RC “Shchaslyvyi” located in Bihova street.
In April, builders completed:
• arrangement of parapet covers;
• chimney capping works (except for the installation of gratings, which will be performed after the facade works on the roof);
• dismantling of the construction crane.
The following works were also carried out during April:
・pouring the foundation of the slab and arranging the monolithic vertical under the parking lot in the third house;
・floor cap (completed on the 17th floor and almost completed on the 16th floor);
・arrangement of a wet facade on cold transitions (reinforcement of walls, application of glue);
・arrangement of the ventilated facade (readiness – 93%);
・plumbing works on heating and cold water piping (on floors 3-10).