Herein it is being told how the construction of the residential complex Crystal Avenue in Petropavlivska Borshchahivka is proceeding.
In the second phase (11-A, Oksamytova St.) interior decoration, installation of suspended ceilings, installation of lamps, fire detectors are fully completed. The decoration of the hall, which is 30% ready, is in progress. Builders are also working on arranging the adjacent territory.
In the fourth phase (1, Kryshtaleva St.) the following works are in progress:
•installation of a ventilated facade (50% completed);
•installation of a wet facade (40% completed);
•arrangement of internal gas supply (50% completed);
•the arrangement of the roof is partially completed (70% completed).
In the fifth phase (1 – B, Kryshtaleva St.) monolithic works on the 17th floor and brickwork on the 9th floor have been completed.